Hello
If you want a report point MRP with reorder point automatically calculated based on the forecast, you should use MRP type V2.
Otherwise, you can try MRP type VV, which is not a reorder point but considers forecast requirements.
BR
Caetano
Hello
If you want a report point MRP with reorder point automatically calculated based on the forecast, you should use MRP type V2.
Otherwise, you can try MRP type VV, which is not a reorder point but considers forecast requirements.
BR
Caetano